Start Date-End Date: 08/01/2012-08/05/2012 Land Manager Office: USFS - Salida Ranger District Land Manager Contact: Ben Lara Funding Partner: Programmatic Partner: Summary: New Trail Construction Description: New Trail Construction Latitude/Longitude: 39.027719,, -106.589355 Additional Information: Camping Available: Yes Physical Difficulty: Difficult High Altitude Project: Yes Desired Number of Volunteers: 30 Total Adult Volunteers Attended: 20 Total Youth Volunteers Attended: 0 Total Volunteer Days: 20 Total Unique Volunteers: 20 Total Volunteer Hours: 800 Staff Hours: 0 Stipend Hours: 0 Project Summary: Successes and Challenges: Lessons Learned: Special Notes: Stewardship Education: Key Concerns or Comments from Staff or Volunteers: Description of Accidents/Incidents: Description of Work Completed: